Managing Pre-Sale Renovations for Lenders and Asset Managers in California: A 2026 Guide
By Orit Gadish, President and Broker, Geffen Real Estate
Last reviewed: November 20, 2026
This guide is general information for lenders, servicers, asset managers and their counsel who own, or are about to own, a California residential property after foreclosure. It is not legal advice. It explains the California rules that sit around a repair or renovation before an REO sale: the duty to maintain, who may do the work, what the contract must say, permits, occupied homes, and the lien rules that follow every dollar spent. It builds on our guide on selling REO (bank-owned) property in California.
Quick answer
Maintaining and renovating are two different questions. California law tells a legal owner to keep a vacant foreclosed house in decent exterior condition: "A legal owner shall maintain vacant residential property purchased by that owner at a foreclosure sale once that sale is deemed final, or acquired by that owner through foreclosure under a mortgage or deed of trust" ( Civil Code § 2929.3(a)(1)). A city or county may fine an owner who does not, up to a maximum of "two thousand dollars ($2,000) per day for the first 30 days" and then "five thousand dollars ($5,000) per day thereafter" ( Civil Code § 2929.3(a)(3)). Nothing in that section tells an owner to remodel. Whether to renovate before listing is a business decision about net proceeds, and this guide covers the rules that apply once the decision is made.
Whoever does the work needs the right license, and the contract has to say the right things. California makes it "a misdemeanor for a person to engage in the business of, or act in the capacity of, a contractor within this state" without a license ( Business and Professions Code § 7028(a)), and a person who hires an unlicensed contractor "may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor" ( Business and Professions Code § 7031(b)). A repair contract with a contractor on a residential property can be a home improvement contract, which has its own required terms, a cap on the down payment and a mechanics lien warning ( Business and Professions Code § 7159). Local building departments decide what needs a permit. In the City of Los Angeles, for example, "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" without a permit ( LAMC § 91.106.1.1), with listed exceptions.
Every contractor, subcontractor and supplier can reach the property through the lien law."A person that provides work authorized for a work of improvement" has a lien right ( Civil Code § 8400), and work is authorized when it is "provided at the request of or agreed to by the owner" ( Civil Code § 8404(a)). Subcontractors and suppliers must give a preliminary notice, and the clocks to record a claim run from completion or from a recorded notice of completion. A lender that tracks notices, collects releases at every payment and records the notice of completion keeps the title clean for the buyer. Geffen Real Estate has 8 offices throughout California and lists property preservation and a pre-sale renovation option among its REO services. If a broker or anyone affiliated with it recommends or coordinates a contractor, ask in writing what the broker is paid in connection with the work.
Key takeaways
- The duty is to maintain, not to renovate. The code requires a legal owner to "maintain vacant residential property" it bought at a foreclosure sale or acquired through foreclosure ( Civil Code § 2929.3(a)(1)), and defines the failure as "failure to care for the exterior of the property" ( Civil Code § 2929.3(b)).
- Before a city fines an owner, it must give notice and time to fix the problem: "not less than 14 business days following the date of the notice" to start the repair ( Civil Code § 2929.3(a)(2)(B)(i)).
- Use licensed contractors, and check each license and each subcontractor. In a dispute over licensing, "the burden of proof to establish licensure or proper licensure shall be on the licensee" ( Business and Professions Code § 7031(d)).
- The small-job exception from licensing is narrow. It covers work "less than one thousand dollars ($1,000)" in total, and only if "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)). It took effect in that form January 1, 2025 ( AB 2622).
- The owner-builder exemption for doing the work yourself does not apply when the improvements are intended for sale: "None of the improvements are intended or offered for sale" ( Business and Professions Code § 7044(a)(1)(A)). A separate exemption for an owner that contracts directly with licensed trades is limited for single-family homes unless the owner hires a licensed general contractor ( Business and Professions Code § 7044(a)(2)). For a lender, the practical path is a licensed general contractor.
- A home improvement contract must be signed before work starts, and "Before any work is started, the contractor shall give the buyer a copy of the contract that is signed and dated by both the contractor and the buyer" ( Business and Professions Code § 7159(c)(3)(A)).
- Pay against the schedule and collect releases. A waiver is "null, void, and unenforceable" unless it is in the statutory form when the claimant is not actually paid ( Civil Code § 8132).
- Record the notice of completion. It must be recorded "on or within 15 days after the date of completion of a work of improvement" ( Civil Code § 8182(a)), and it shortens the lien deadlines.
- If a tenant lives in the house, entry for repairs needs notice: "Twenty-four hours shall be presumed to be reasonable notice in absence of evidence to the contrary" ( Civil Code § 1954(d)(1)).
- Examples in this guide that use days or dollar figures are illustrations, not market data.
Plain-English glossary
- Legal owner. The lender or other holder that owns the property after a foreclosure sale. The maintenance statute applies to a legal owner of vacant residential property.
- Preservation. Work that keeps the property from losing value or becoming a nuisance: securing it, stopping leaks, exterior upkeep, yard and pool care.
- Renovation. Work meant to raise the sale price or to make the home saleable to more buyers, such as flooring, paint, kitchens and bathrooms.
- Direct contractor. A contractor with "a direct contractual relationship with an owner" ( Civil Code § 8018). Often called the prime or general contractor.
- Subcontractor. A contractor without "a direct contractual relationship with an owner" ( Civil Code § 8046).
- Preliminary notice. The written notice that a subcontractor or supplier must give the owner, the direct contractor and any construction lender to protect lien rights.
- Mechanics lien. A claim recorded against the property by a person who provided work and was not paid. It is called a claim of lien in the code.
- Notice of completion. A notice the owner records after the work ends. It starts shorter deadlines for lien claimants.
- CSLB. The Contractors State License Board, the state agency that licenses contractors. Its site lets you "Look up a contractor license or Home Improvement Salesperson (HIS) registration to verify information, including complaint disclosure" ( CSLB, Check a License).
Which rule applies? A quick map
| Question | Where the rule is | What it says in short |
|---|---|---|
| Must a lender keep a vacant REO in shape? | Civil Code § 2929.3 | Yes for vacant residential property, with notice and time to cure before any fine |
| Can a city bill for cleanup it does itself? | Civil Code § 2929.45 | Costs "shall not exceed the actual and reasonable costs of nuisance abatement" ( § 2929.45(a)) |
| Who may do contractor work? | B&P § 7028, § 7026 | Licensed contractors; the definition includes subcontractors and specialty contractors |
| Is there a small-job exception? | B&P § 7048 | Under $1,000 total, no building permit needed, no advertising as a contractor, no employees |
| What must the repair contract say? | B&P § 7159, § 7159.5 | Written, signed before work, license number, change orders in writing, down payment cap, lien warning |
| Is a permit needed? | Local building code, such as LAMC § 91.106 | Set by the city or county where the property sits |
| Who can claim a lien? | Civil Code § 8400, § 8404 | Direct contractors, subcontractors, suppliers, laborers and design professionals who provided authorized work |
| How do you shorten lien deadlines? | Civil Code §§ 8180 to 8190 | Record a notice of completion and send copies |
| How long does a lien last? | Civil Code § 8460 | The claimant must sue within 90 days after recording the claim |
| May a vendor enter an occupied unit? | Civil Code § 1954 | With written notice stating date, approximate time and purpose |
Typical sequence
- Confirm title, occupancy and the legal owner's maintenance duty. See the REO guide for finality of the sale.
- Secure and preserve the property so it never becomes a nuisance.
- Get the condition picture: inspection, scope, and a price opinion for the as-is and repaired scenarios.
- Decide what is preservation, what is health and safety, and what is renovation.
- Collect bids from licensed contractors on the same scope, and check each license.
- Check the permit requirements with the local building department before work starts.
- Sign a written contract that meets Business and Professions Code § 7159 before work starts.
- Manage the job: change orders in writing, progress payments against the schedule, releases with each payment.
- At completion, record the notice of completion and send the required copies.
- List and sell, with the repair file ready for the buyer's questions.
Step 1: Know what the code requires of a legal owner
The maintenance statute applies to residential property that is vacant. A legal owner "shall maintain vacant residential property purchased by that owner at a foreclosure sale once that sale is deemed final, or acquired by that owner through foreclosure under a mortgage or deed of trust" ( Civil Code § 2929.3(a)(1)). The same section says it "shall only apply to residential real property" ( Civil Code § 2929.3(g)).
The statute defines the failure narrowly. "Failure to maintain" means "failure to care for the exterior of the property," and the examples include "failing to take action to prevent trespassers or squatters from remaining on the property" ( Civil Code § 2929.3(b)). That is a maintenance and security standard. It is not a renovation standard.
The code also protects the owner who responds. Before a fine, the governmental entity must give a notice that includes the alleged violation and "a detailed description of the conditions that gave rise to the allegation" ( Civil Code § 2929.3(a)(2)(A)). In setting the amount, it "shall take into consideration any timely and good faith efforts by the legal owner to remedy the violation" ( Civil Code § 2929.3(a)(3)). A separate section requires "a notice of the violation and an opportunity to correct that violation" before a fine or penalty ( Civil Code § 2929.4(a)), with an exception where "a specific condition of the property threatens public health or safety" ( Civil Code § 2929.4(b)).
Local ordinances add to this. The statute says "These provisions shall not preempt any local ordinance" ( Civil Code § 2929.3(f)). Our REO guide covers the Los Angeles foreclosure registry and inspection duties in detail.
Step 2: Decide what kind of work this is
Sort every line item into one of three groups before you ask for bids.
- Preservation and security. Securing doors and windows, stopping active leaks, clearing debris, yard and pool care. This work answers the maintenance duty in Step 1.
- Health, safety and code items. Work that a city could cite, or that would make the home unsafe for a buyer.
- Renovation. Cosmetic and functional upgrades meant to widen the buyer pool or raise the price.
The first two groups are driven by the property's condition and by the code. The third is driven by the numbers: what the renovation costs, how long it adds to the holding period, and what it is expected to add to the sale price. Illustration only, not market data: a lender compares a $500,000 as-is offer with a $525,000 expected price after $12,000 of work and $4,000 of extra carrying cost. The difference is $25,000 minus $16,000, or $9,000 before sale costs. If the expected price after work were $510,000, the same work would lose money: $10,000 minus $16,000 is a $6,000 loss before sale costs. A broker's price opinion for each scenario gives the real inputs.
Step 3: Who may do the work
California licenses contractors, and the definition is wide. A contractor is "any person who undertakes to or offers to undertake to, or purports to have the capacity to undertake to, or submits a bid to, or does himself or herself or by or through others, construct, alter, repair, add to, subtract from, improve, move, wreck or demolish any building" ( Business and Professions Code § 7026), and the term "includes subcontractor and specialty contractor" ( Business and Professions Code § 7026).
Acting as a contractor without a license is a crime: "it is a misdemeanor for a person to engage in the business of, or act in the capacity of, a contractor within this state" when "The person is not licensed in accordance with this chapter" ( Business and Professions Code § 7028(a)). A first conviction is "punishable by a fine not exceeding five thousand dollars ($5,000) or by imprisonment in a county jail not exceeding six months, or by both that fine and imprisonment" ( Business and Professions Code § 7028(b)). The statute also treats the person who hired the unlicensed worker as a victim: "a person who utilized the services of the unlicensed person is a victim of crime" ( Business and Professions Code § 7028(h)).
The civil side matters more to an owner. An unlicensed contractor generally cannot sue for payment, because the statute bars a contractor from bringing an action "without alleging that they were a duly licensed contractor at all times during the performance of that act or contract" ( Business and Professions Code § 7031(a)). The owner can recover what it paid: "a person who utilizes the services of an unlicensed contractor may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor for performance of any act or contract" ( Business and Professions Code § 7031(b)). A security interest taken for that work "is unenforceable if the person performing the act or contract was not a duly licensed contractor at all times during the performance of the act or contract" ( Business and Professions Code § 7031(c)).
The owner-builder exemption. The exemption for an owner who does the work personally or with the owner's own employees does not apply when the improvements are intended for sale. It requires that "None of the improvements are intended or offered for sale" ( Business and Professions Code § 7044(a)(1)(A)), and that "The property owner personally performs all of the work or any work not performed by the owner is performed by the owner's employees with wages as their sole compensation" ( Business and Professions Code § 7044(a)(1)(B)). A separate exemption covers an owner that contracts directly with licensed trade contractors: "The owner directly contracts with licensees who are duly licensed to contract for the work of the respective trades involved in completing the project" ( Business and Professions Code § 7044(a)(2)(A)). For single-family homes that exemption is limited: "no more than four of these structures are intended or offered for sale in a calendar year," and the limit "shall not apply if the owner contracts with a general contractor for the construction" ( Business and Professions Code § 7044(a)(2)(B)). Proof that five or more structures were sold or offered for sale within a year after completion "constitutes a conclusive presumption that the structures were undertaken for purposes of sale" ( Business and Professions Code § 7044(b)(2)). For a lender, the practical path is a licensed general contractor.
Project managers and coordinators count too. A "consultant" is a contractor, and for home improvement work a consultant includes a person, other than the owner, who "Provides or oversees a bid for a construction project" or who "Arranges for and sets up work schedules for contractors and subcontractors and maintains oversight of a construction project" ( Business and Professions Code § 7026.1(a)(2)(B)). Paying an unlicensed project manager or renovation coordinator carries the same payment risk as paying an unlicensed contractor ( Business and Professions Code § 7031(b)). If a broker or anyone affiliated with it recommends or coordinates the contractor, ask in writing what the broker is paid in connection with the work, and get competing bids. A licensee must not fail "to reveal to the buyer or seller contracting with the licensee the full amount of the licensee's compensation, commission, or profit" before the agreement is signed ( Business and Professions Code § 10176(g)). A trustee "shall exercise prudence in" "Selecting an agent" ( Probate Code § 16052(a)).
The small-job exception. The licensing chapter does not apply to work where "the aggregate contract price for labor, materials, and all other items is less than one thousand dollars ($1,000)," but only if "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)). The $1,000 figure, the building-permit condition and the employee condition took effect January 1, 2025 ( AB 2622, Stats. 2024, ch. 240); the section was amended again effective January 1, 2026 (Stats. 2025, ch. 67, per the section's history line). Splitting a job to fit under the limit is addressed directly: the exception does not apply where "a division of the operation is made in contracts of amounts less than one thousand dollars ($1,000) for the purpose of evasion of this chapter or otherwise" ( Business and Professions Code § 7048(b)). It also does not apply to a person who "Advertises or puts out a sign or card or other device that might indicate to the public that the person is a contractor" or who "Employs another person to perform, or assist in performing, the work or operation" ( Business and Professions Code § 7048(c)).
Classification. A license has a classification. A general building contractor's business is work "requiring in its construction the use of at least two unrelated building trades or crafts" ( Business and Professions Code § 7057(a)), and the board may "limit the field and scope of the operations of a licensed contractor to those in which they are classified and qualified to engage" ( Business and Professions Code § 7059(a)). When you check a license, check that its classification matches the trade. Our guide on permits, contractor licensing and bids for pre-sale repairs covers licensing, permits and bids in more detail.
Step 4: Check the license, the bond and the insurance
The CSLB tells consumers: "Contractors are required to have their license number on their business card and on all bids and contracts" and "Seeing a license number doesn't necessarily mean the license is valid" ( CSLB, How do I find the right licensed contractor?). Check each one on the board's license lookup.
Two requirements sit behind the license. The first is a bond. The board must require "a contractor's bond in the sum of twenty-five thousand dollars ($25,000)" ( Business and Professions Code § 7071.6(a)), and the CSLB cautions that "Bonds do not assure the financial or professional integrity or competency of a contractor" ( CSLB). The bond protects a narrow group first. For claims other than those of the beneficiaries listed in § 7071.5(a), including "A homeowner contracting for home improvement upon the homeowner's personal family residence damaged as a result of a violation of this chapter by the licensee" ( Business and Professions Code § 7071.5(a)), "the aggregate liability of a surety on claims brought against a bond required by this section shall not exceed the sum of seven thousand five hundred dollars ($7,500)" ( Business and Professions Code § 7071.6(b)).
The second is workers' compensation. A licensee must "have on file at all times a current and valid Certificate of Workers' Compensation Insurance or Certification of Self-Insurance in the applicant's or licensee's business name" ( Business and Professions Code § 7125(a)). The exception is narrow: the section does not apply to a licensee who meets "both of the following conditions" ( Business and Professions Code § 7125(b)). The first is that the licensee "Has no employees" and files a statement saying so ( § 7125(b)(1)). The second is that the licensee "Does not hold a C-8 license" (concrete), "a C-20 license" (HVAC), "a C-22 license" (asbestos abatement), "a C-39 license" (roofing), "or a D-49 license" (tree service) ( § 7125(b)(2)). So a contractor with no employees still needs the certificate if it holds one of those licenses. This version of the section "shall remain in effect only until January 1, 2028" ( § 7125(i)). Under the version operative January 1, 2028, the exemption for a licensee with no employees ends for everyone except a joint venture: "This section does not apply to an applicant or licensee organized as a joint venture pursuant to Section 7029 that has no employees" ( § 7125(b), operative January 1, 2028).
Keep a copy of the license check, the insurance certificate and the subcontractor list in the property file. For a lender, that file answers questions later from the buyer, the title company and the lender's own audit.
Step 5: Bids and scope
The CSLB advises: "Get at least three written bids on your project, and make sure you're comparing bids based on identical plans, specifications, and scope of work" and "Do not automatically accept the lowest bid" ( CSLB). For an asset manager, that means writing one scope that every bidder prices. The scope should break out each room or area, say who pulls any permit, and separate labor and materials. Those are practical items, not requirements in the sections quoted here.
If a broker, asset manager or coordinator offers to handle the bids, see the licensing and compensation points in Step 3. Geffen Real Estate's REO and Default Solutions page lists a renovation option before sale, and geffen's property management page lists a network of licensed, bonded and fully insured contractors who have been vetted for good pricing and work that is up to code.
Step 6: Permits
Permit rules are local. The state licensing law ties its small-job exception to permits ("the work or operation does not require a building permit," Business and Professions Code § 7048(a)), and the building department of the city or county where the property sits decides what needs one.
The City of Los Angeles is a useful example. Its municipal code says "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" and continues "unless said person has obtained a permit therefor from the department" ( LAMC § 91.106.1.1). It lists work that needs no permit, which includes "Work regulated by this Code that is valued at $2,500 or less, unless it impacts the structural stability of a building, affects public safety, is performed to comply with a Department order, or involves a change in the use or occupancy" ( LAMC § 91.106.2). The code adds that "Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of the City of Los Angeles" ( LAMC § 91.106.2). Other cities and counties have their own lists and thresholds.
The Los Angeles Department of Building and Safety publishes a list of work that can get an express permit without plan check: "Following are the lists of different types of construction for which an express permit can be issued" ( LADBS Information Bulletin P/GI 2026-003, revised June 10, 2026). The list includes "Kitchen/bathroom remodel for residential buildings (no structural changes)" and "Replacing water heaters" ( LADBS Information Bulletin P/GI 2026-003). Whether a particular job qualifies is for LADBS to say.
Inspections follow the permit. LADBS describes its role this way: "We review plans, issue permits, and inspect the work," and notes "You may obtain the permit as an Agent, an Owner, or a Contractor" ( LADBS). The code says "The issuance of a permit is not an approval or an authorization of the work specified therein" ( LAMC § 91.106.4.3.1), so a permit is the start of the inspection process.
Step 7: The repair contract
If the contract is between a contractor and an owner for work on residential property, the home improvement statutes apply on their face. "Home improvement" means "the repairing, remodeling, altering, converting, or modernizing of, or adding to, residential property" ( Business and Professions Code § 7151(a)). A home improvement contract is "an agreement, whether oral or written, or contained in one or more documents, between a contractor and an owner" for that work, where the aggregate price "exceeds five hundred dollars ($500)" ( Business and Professions Code § 7159(b)).
The main requirements, in plain terms:
- Written and signed before work."A home improvement contract and any changes to the contract shall be in writing and signed by the parties to the contract prior to the commencement of work" ( Business and Professions Code § 7159(d)).
- Contractor identity. It must include "The name, business address, and license number of the contractor" ( Business and Professions Code § 7159(d)(1)).
- Change orders in writing."A change-order form for changes or extra work shall be incorporated into the contract and shall become part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by a change order" ( Business and Professions Code § 7159(c)(5)).
- Bond notice. The contract must include "a notice stating that the owner or tenant has the right to require the contractor to have a performance and payment bond" ( Business and Professions Code § 7159(c)(6)).
- Subcontractors."The contract shall contain a statement regarding whether or not a subcontractor will be used on the project" ( Business and Professions Code § 7159(c)(7)(A)).
- Down payment cap. The contract says "THE DOWNPAYMENT MAY NOT EXCEED $1,000 OR 10 PERCENT OF THE CONTRACT PRICE, WHICHEVER IS LESS" ( Business and Professions Code § 7159(d)(8)(C)), and a companion section says "the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less" ( Business and Professions Code § 7159.5(a)(3)).
- Progress payments tied to work. The required statement reads "IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED" ( Business and Professions Code § 7159(d)(9)(C)).
- Lien releases. The contract must include a statement that after satisfactory payment for a portion of the work, the contractor "shall furnish to the person contracting for the home improvement or swimming pool work a full and unconditional release from any potential lien claimant claim or mechanics lien" for the portion paid ( Business and Professions Code § 7159(c)(4)).
- Right to cancel. Unless the contract was "Negotiated at the contractor's place of business" or another listed exception applies, the buyer must get a notice entitled "Three-Day Right to Cancel," or "Five-Day Right to Cancel" for a senior citizen. The notice says "You, the buyer, have the right to cancel this contract within three business days" ( Business and Professions Code § 7159(e)(6)). Plan the start date around it.
- Bonded contractors. A contractor "furnishing a performance and payment bond, lien and completion bond, or a bond equivalent or joint control approved by the registrar covering full performance and payment is exempt from paragraphs (3), (4), and (5)" of the down payment and progress payment rules ( Business and Professions Code § 7159.5(a)(8)).
- Mechanics lien warning. The notice in the contract begins "Anyone who helps improve your property, but who is not paid, may record what is called a mechanics lien on your property" and warns that "Even if you pay your contractor in full, unpaid subcontractors, suppliers, and laborers who helped to improve your property may record mechanics liens and sue you in court to foreclose the lien" ( Business and Professions Code § 7159(e)(4)).
Releases under the companion section are furnished "if requested" ( Business and Professions Code § 7159.5(a)(6)), so ask for them with each payment. The statute is long and has more required headings, notices and dates. Review a contract template against the current text of § 7159 before first use.
Step 8: Occupied properties
Some REO properties are occupied when repairs are planned. The landlord entry statute lists "To make necessary or agreed repairs, decorations, alterations or improvements" among the permitted reasons for entry ( Civil Code § 1954(a)(2)). The notice must be in writing and "shall include the date, approximate time, and purpose of the entry" ( Civil Code § 1954(d)(1)), and "Twenty-four hours shall be presumed to be reasonable notice in absence of evidence to the contrary" ( Civil Code § 1954(d)(1)). Entry is only "during normal business hours" unless the tenant consents ( Civil Code § 1954(b)), and the landlord "may not abuse the right of access or use it to harass the tenant" ( Civil Code § 1954(c)). Mailing the notice "at least six days prior to an intended entry" is presumed reasonable ( Civil Code § 1954(d)(1)). Occupancy raises separate eviction and relocation questions that this guide does not cover. When an eviction is involved, the eviction attorney handles the unlawful detainer case, and Geffen monitors the eviction attorney's work on behalf of its clients.
Step 9: Pay in a way that protects the title
The lien law is the reason pre-sale work needs discipline. Three rules do most of the work.
Who can claim. A lien right belongs to a person who "provides work authorized for a work of improvement," including "Direct contractor," "Subcontractor," "Material supplier," "Equipment lessor," "Laborer," and "Design professional" ( Civil Code § 8400). Work is authorized when "It is provided at the request of or agreed to by the owner" or when "It is provided or authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of all or part of the work of improvement or site improvement" ( Civil Code § 8404). That second category matters to an owner who uses a project manager: work ordered by the project manager is authorized work. The same applies if the listing broker or any coordinator is "having charge" of the work: its orders can make the work authorized for lien purposes ( Civil Code § 8404(b)). Keep change orders in the owner's name and in writing.
Preliminary notice. Before recording a lien claim, "a claimant shall give preliminary notice to the following persons" ( Civil Code § 8200(a)): the owner, the direct contractor and any construction lender. It must be given "not later than 20 days after the claimant has first furnished work on the work of improvement" ( Civil Code § 8204(a)). A late notice limits the claim to "work performed within 20 days prior to the service of the preliminary notice, and at any time thereafter" ( Civil Code § 8204(a)). Laborers and the direct contractor are not required to give one: "A laborer is not required to give preliminary notice" and a claimant with a direct contract with the owner gives it "only to the construction lender or reputed construction lender, if any" ( Civil Code § 8200(e)). The notice carries a warning to the owner: "EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property" ( Civil Code § 8202(a)(3)). A claimant "may enforce a lien only if the claimant has given preliminary notice to the extent required" and "made proof of notice" ( Civil Code § 8410).
Releases. The statute voids a promise to waive someone else's lien rights: "An owner, direct contractor, or subcontractor may not, by contract or otherwise, waive, affect, or impair any other claimant's rights under this part" ( Civil Code § 8122). A claimant's own release works only in the statutory form. For a progress payment where the claimant is not actually paid, the release is "null, void, and unenforceable unless it is in substantially the following form" ( Civil Code § 8132), and the form is headed CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT. The CSLB's consumer guidance puts it simply: "Before making a payment, get a signed conditional release from the possible lien claimants," and "By law, you may withhold the next payment until you get the unconditional releases for the previous payment" ( CSLB, How to Prevent a Mechanics Lien). The same page calls joint checks "the simplest way to prevent liens and ensure that subcontractors and suppliers are paid" ( CSLB).
Step 10: Close out the job and record the notice of completion
Completion has a legal meaning. It occurs on any of these events: "Actual completion of the work of improvement," "Occupation or use by the owner accompanied by cessation of labor," "Cessation of labor for a continuous period of 60 days," or "Recordation of a notice of cessation after cessation of labor for a continuous period of 30 days" ( Civil Code § 8180(a)).
The owner may record a notice of completion "on or within 15 days after the date of completion of a work of improvement" ( Civil Code § 8182(a)). It "shall be signed and verified by the owner" ( Civil Code § 8182(b)), and "A notice of completion that does not comply with the provisions of this section is not effective" ( Civil Code § 8182(d)).
The notice shortens the deadlines. A direct contractor must record a claim of lien before the earlier of "Ninety days after completion of the work of improvement" or "Sixty days after the owner records a notice of completion or cessation" ( Civil Code § 8412). Other claimants must record before the earlier of "Ninety days after completion of the work of improvement" or "Thirty days after the owner records a notice of completion or cessation" ( Civil Code § 8414).
| Illustration (days counted from completion) | Direct contractor deadline | Subcontractor or supplier deadline |
|---|---|---|
| No notice of completion recorded | Day 90 | Day 90 |
| Notice of completion recorded on day 10 | Day 70 | Day 40 |
The table is an illustration of how §§ 8412 and 8414 work, not a calendar for any particular job.
An owner that records the notice "shall, within 10 days of the date the notice of completion or cessation is filed for record, give a copy of the notice" to the direct contractor and to each claimant that gave preliminary notice ( Civil Code § 8190(a)). If the owner fails to do so, "the notice is ineffective to shorten the time within which that person may record a claim of lien under Sections 8412 and 8414" ( Civil Code § 8190(c)). Section 8190(d) lists owners to whom the duty does not apply, including "A person that has a security interest in the property" and "A person that obtains an interest in the property pursuant to a transfer described in subdivision (b), (c), or (d) of Section 1102.2" ( Civil Code § 8190(d)). Section 1102.2 describes, among other transfers, "sales by any foreclosure sale" ( Civil Code § 1102.2(b)) and "any foreclosure sale after default" ( Civil Code § 1102.2(c)). Read together, § 8190(d)(3) and § 1102.2(c) indicate that a lender that took title at its own trustee's sale or by a deed in lieu of foreclosure is not subject to the 10-day copy duty. Section 8190(d) says the section does not apply to "A person that obtains an interest in the property pursuant to a transfer described in subdivision (b), (c), or (d) of Section 1102.2" ( Civil Code § 8190(d)(3)), and § 1102.2(c) covers "sales to a beneficiary of a deed of trust by a trustor or successor in interest who is in default" and sales "by a mortgagee or a beneficiary under a deed of trust who has acquired the real property at a sale conducted pursuant to a power of sale" ( Civil Code § 1102.2(c)). For an owner that is subject to the duty, not giving the copies means the notice is ineffective to shorten the claimant's time, which "is the sole liability of the owner for failure to give notice" ( Civil Code § 8190(c)). Some lenders send the copies anyway, because it costs little and removes any argument about the deadline. Ask counsel how your institution handles it. Whether or not the copy duty applies to a particular owner, the deadlines in §§ 8412 and 8414 show why an owner records the notice and keeps proof of the dates.
If a lien is recorded. A claim of lien must be "signed and verified by the claimant" and a copy must be served on the owner: "A copy of the claim of mechanics lien, which includes the Notice of Mechanics Lien required by paragraph (8) of subdivision (a), shall be served on the owner or reputed owner" ( Civil Code § 8416(c)). Failure to serve "shall cause the claim of mechanics lien to be unenforceable as a matter of law" ( Civil Code § 8416(e)). The claimant has a short window to sue: "The claimant shall commence an action to enforce a lien within 90 days after recordation of the claim of lien. If the claimant does not commence an action to enforce the lien within that time, the claim of lien expires and is unenforceable" ( Civil Code § 8460(a)). The lender's attorney handles any lien dispute and any petition to release a lien under the code's release-order procedure.
How Geffen Real Estate can help
Geffen Real Estate handles California probate, trust, conservatorship, receivership, bankruptcy and REO sales, and lists property management among its services. The services on our site that matter to a pre-sale renovation include:
- Secure property and property preservation. On our REO and Default Solutions page, we list determining whether a property is vacant or occupied, securing it if vacant, and property preservation.
- Pre-sale renovation. Our REO and Default Solutions page lists a renovation option before sale. See that page for the current description.
- BPO and BOV. We provide a valuation of the asset, which can compare the as-is and repaired scenarios.
- Contractor network. On our property management page, we list a network of licensed, bonded and fully insured contractors who have been vetted for good pricing and work that is up to code.
- Renovate now, pay at closing. On our probate, trust and conservatorship page, we list repairs done first with the cost paid at the close of escrow. The page describes this for probate, trust and conservatorship sales.
- Multi-channel marketing, offer management and escrow management once the property is ready to list.
- Evictions. The eviction attorney handles the unlawful detainer case, and Geffen monitors the eviction attorney's work on behalf of its clients.
Before using any renovation program, ask who signs the contract with the contractor and who holds the contractor license, and see the licensing and compensation points in Step 3. If Geffen or any broker is paid anything connected with the repairs, the full amount must be disclosed in writing before you sign ( Business and Professions Code § 10176(g)).
These services are optional. They do not guarantee a higher price, a faster sale or a particular result, and they are not legal advice.
Frequently asked questions
Does a lender have to renovate a foreclosed house before selling it in California?
No. The code requires a legal owner to maintain vacant residential property bought at a foreclosure sale, and it defines the failure as "failure to care for the exterior of the property" ( Civil Code § 2929.3(b)). It does not require renovation. Whether to renovate is a decision about net proceeds.
How much can a city fine a lender for not maintaining an REO?
The code allows "Up to a maximum of two thousand dollars ($2,000) per day for the first 30 days" and "Up to a maximum of five thousand dollars ($5,000) per day thereafter" ( Civil Code § 2929.3(a)(3)). The fine starts only after the period to remedy the violation ends, and the entity must allow "a hearing and opportunity to contest any fine imposed" ( Civil Code § 2929.3(a)(3)).
Does a city have to give the lender notice and time to fix a violation before a fine?
Yes. A governmental entity "shall provide the owner of that property with a notice of the violation and an opportunity to correct that violation" ( Civil Code § 2929.4(a)). The exception is a condition that "threatens public health or safety" ( Civil Code § 2929.4(b)). Under the maintenance statute the notice must give the owner time to start the repair, "not less than 14 business days following the date of the notice," and the entity must extend that period by 10 business days if the owner asks to clarify the needed actions ( Civil Code § 2929.3(a)(2)(B)(i)). A second period of at least 16 business days to complete the work follows.
Can a city charge a lender for cleaning up a vacant REO itself?
Yes, within limits. An assessment or lien for nuisance abatement costs "shall not exceed the actual and reasonable costs of nuisance abatement" ( Civil Code § 2929.45(a)), and the costs must have been adopted by the elected officials at a public hearing ( Civil Code § 2929.45(b)).
Do I need a licensed contractor to repair a bank-owned house in California?
Generally yes. California makes it "a misdemeanor for a person to engage in the business of, or act in the capacity of, a contractor within this state" without a license ( Business and Professions Code § 7028(a)). The definition of contractor covers anyone who will "construct, alter, repair, add to, subtract from, improve" a building, and includes subcontractors and specialty contractors ( Business and Professions Code § 7026).
What happens if a lender hires an unlicensed contractor?
The lender can sue to recover what it paid: "a person who utilizes the services of an unlicensed contractor may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor for performance of any act or contract" ( Business and Professions Code § 7031(b)). The contractor generally cannot sue for payment ( Business and Professions Code § 7031(a)).
Is there any repair work a lender can hire out without a licensed contractor?
Only small jobs. The licensing chapter does not apply where the total is "less than one thousand dollars ($1,000)," and "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)). The exception does not apply to a person who "Advertises or puts out a sign or card or other device that might indicate to the public that the person is a contractor" or who employs another person to do the work ( Business and Professions Code § 7048(c)).
Does a lender need a contractor's license to manage REO repairs itself?
A lender that hires licensed contractors does not need its own license for that. The exemption for doing the work yourself requires that "None of the improvements are intended or offered for sale" ( Business and Professions Code § 7044(a)(1)(A)). A separate exemption applies where the owner "directly contracts with licensees who are duly licensed to contract for the work of the respective trades" ( Business and Professions Code § 7044(a)(2)(A)), but for single-family homes it is limited to four homes offered for sale in a calendar year unless the owner hires a licensed general contractor ( Business and Professions Code § 7044(a)(2)(B)). A person who "Provides or oversees a bid" or schedules and supervises contractors on a home improvement project can itself be a contractor ( Business and Professions Code § 7026.1(a)(2)(B)). The practical path is a licensed general contractor.
How do I check a contractor's license in California?
Use the Contractors State License Board's license lookup. It lets you "Look up a contractor license or Home Improvement Salesperson (HIS) registration to verify information, including complaint disclosure" ( CSLB). Also check the classification against the work, and ask each subcontractor for its license number.
What is the contractor license bond, and does it protect the lender?
Licensed contractors must have "a contractor's bond in the sum of twenty-five thousand dollars ($25,000)" on file ( Business and Professions Code § 7071.6(a)). The CSLB cautions that "Bonds do not assure the financial or professional integrity or competency of a contractor" ( CSLB). A contract can also require a performance and payment bond: the home improvement contract must tell the owner it has "the right to require the contractor to have a performance and payment bond" ( Business and Professions Code § 7159(c)(6)).
Does a repair contract for a bank-owned house have to be in writing?
If it is a home improvement contract, yes. It "shall be in writing and signed by the parties to the contract prior to the commencement of work covered by the contract" ( Business and Professions Code § 7159(d)). The definition covers an agreement "between a contractor and an owner" for the repair of residential property above $500 ( Business and Professions Code § 7159(b); § 7151(a)).
How much can a contractor ask for as a down payment, and can it collect for work not yet done?
The statute says "the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less" ( Business and Professions Code § 7159.5(a)(3)). The required contract statement reads "IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED" ( Business and Professions Code § 7159(d)(9)(C)), so payments follow a schedule tied to described work. The cap and the progress-payment rules do not apply to a contractor that furnishes an approved performance and payment bond ( Business and Professions Code § 7159.5(a)(8)).
Does a lender need a building permit for pre-sale repairs?
It depends on the work and the local code. The Los Angeles Department of Building and Safety publishes a list of work that can get an express permit without plan check: "Following are the lists of different types of construction for which an express permit can be issued" ( LADBS Information Bulletin P/GI 2026-003, revised June 10, 2026). The list includes "Kitchen/bathroom remodel for residential buildings (no structural changes)" and "Replacing water heaters" ( LADBS Information Bulletin P/GI 2026-003). Whether a particular job qualifies is for LADBS to say. In the City of Los Angeles, "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" without a permit ( LAMC § 91.106.1.1), with exceptions such as work "valued at $2,500 or less" unless it affects structure, safety or use ( LAMC § 91.106.2). Other cities and counties set their own rules, so check with the building department where the property is.
Who can record a mechanics lien on an REO property?
A "Direct contractor," "Subcontractor," "Material supplier," "Equipment lessor," "Laborer," or "Design professional" who provided authorized work ( Civil Code § 8400). Work is authorized when it is "provided at the request of or agreed to by the owner" or provided or authorized by a direct contractor, subcontractor, architect or project manager ( Civil Code § 8404).
What is a preliminary notice, and when does a subcontractor have to give it?
It is the notice a claimant gives the owner, the direct contractor and any construction lender before recording a lien claim ( Civil Code § 8200(a)). It must be given "not later than 20 days after the claimant has first furnished work on the work of improvement" ( Civil Code § 8204(a)). A direct contractor and a laborer do not have to give it to the owner ( Civil Code § 8200(e)).
How long does a contractor have to record a mechanics lien, and how long does it last?
A direct contractor has until the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation ( Civil Code § 8412). Other claimants have until the earlier of 90 days after completion or 30 days after the notice is recorded ( Civil Code § 8414). After recording, the claimant "shall commence an action to enforce a lien within 90 days after recordation of the claim of lien," or the claim "expires and is unenforceable" ( Civil Code § 8460(a)). An extension of credit can change that, as the same section explains in subdivision (b).
What is a notice of completion, and should a lender record one?
It is an owner's signed and verified notice recorded "on or within 15 days after the date of completion of a work of improvement" ( Civil Code § 8182(a)). Recording it starts the shorter lien deadlines in §§ 8412 and 8414, which is why an owner that wants a clean title for the sale records one and keeps proof of the dates.
What lien waivers should a lender collect with each payment?
Use the statutory forms. A conditional waiver and release on a progress payment is enforceable only if it is "in substantially the following form" ( Civil Code § 8132), and the code has parallel forms for final payments ( Civil Code § 8136). The CSLB's guidance is to get a conditional release before paying and an unconditional release after ( CSLB).
Can a vendor enter an occupied REO to do repairs?
Yes, with notice. A landlord may enter "To make necessary or agreed repairs, decorations, alterations or improvements" ( Civil Code § 1954(a)(2)), after written notice stating the date, approximate time and purpose, and "Twenty-four hours shall be presumed to be reasonable notice in absence of evidence to the contrary" ( Civil Code § 1954(d)(1)).
Does Geffen have a contractor network for pre-sale work on REO properties?
Our property management page lists a network of licensed, bonded and fully insured contractors, and our REO and Default Solutions page lists a renovation option before sale. These are optional services, and we do not promise a particular outcome. Whoever you hire, check the license, get competing bids, and ask in writing what any broker is paid in connection with the work ( Business and Professions Code § 10176(g)).
Does Geffen serve all of California?
Geffen Real Estate has 8 offices throughout California, with headquarters at 9171 Wilshire Blvd #500, Beverly Hills, CA 90210. Geffen serves commercial clients across California. Call 323-934-1430 to talk about a specific property.
Do I have to disclose unpermitted work when selling an REO?
Check with counsel for the rules that apply to your sale. A sale by a beneficiary that acquired the property at its own power-of-sale sale is one of the transfers listed in the transfer disclosure article's exemptions ( Civil Code § 1102.2(c)). The listing broker's duty is separate: for one to four units, the broker must "conduct a reasonably competent and diligent visual inspection of the property offered for sale and to disclose to that prospective buyer all facts materially affecting the value or desirability of the property that an investigation would reveal" ( Civil Code § 2079(a)).
Can a lender start repairs before the trustee's sale is final?
The maintenance duty in the statute applies to property bought at a foreclosure sale "once that sale is deemed final" ( Civil Code § 2929.3(a)(1)). Before that, whether a lender or servicer may enter or repair depends on the loan documents and the stage of the foreclosure, so ask the lender's counsel first. Our guide on selling REO property in California covers what happens after the sale.
Can my real estate agent manage the repairs?
Be careful. A person other than the owner who "Provides or oversees a bid for a construction project" or "Arranges for and sets up work schedules for contractors and subcontractors and maintains oversight of a construction project" is treated as a contractor for home improvement work ( Business and Professions Code § 7026.1(a)(2)(B)). Ask who signs the contract with the contractor and who holds the license. If the agent is paid anything connected with the work, the licensee must reveal "the full amount of the licensee's compensation, commission, or profit" before the agreement is signed ( Business and Professions Code § 10176(g)). Get competing bids either way.
What is a three-day right to cancel on a repair contract?
For a home improvement contract, the buyer must get a notice entitled "Three-Day Right to Cancel" ("Five-Day Right to Cancel" for a senior citizen) unless the contract was "Negotiated at the contractor's place of business" or another listed exception applies. It says "You, the buyer, have the right to cancel this contract within three business days" ( Business and Professions Code § 7159(e)(6)). Plan the start date around it.
Talk with Geffen Real Estate
If you are a lender, servicer, asset manager or attorney with a California property to prepare and sell, we are glad to talk it through. Call 323-934-1430. Our team answers this line 24 hours a day, 7 days a week. You can also use the contact page. Geffen Real Estate has 8 offices throughout California, with headquarters at 9171 Wilshire Blvd #500, Beverly Hills, CA 90210.
The offices are:
- Beverly Hills (headquarters): 9171 Wilshire Blvd #500, Beverly Hills, CA 90210
- Sacramento: 2740 Fulton Ave, Sacramento, CA 95821
- San Diego: 10089 Willow Creek Rd #200, San Diego, CA 92131
- Irvine: 2102 Business Center Dr #130, Irvine, CA 92612
- San Jose: 2570 N First St, San Jose, CA 95131
- Santa Barbara: 351 Paseo Nuevo, Santa Barbara, CA 93101
- Riverside: 3610 Central Ave #400, Riverside, CA 92506
- Palm Springs: 750 N Palm Canyon Dr #200, Palm Springs, CA 92262
All offices may be reached at 323-934-1430.
About the author
Orit Gadish is the President and broker of Geffen Real Estate (DRE 01505675). The firm has 8 offices throughout California, with headquarters in Beverly Hills, and handles probate, trust, conservatorship and other court-supervised real estate sales as well as REO and default dispositions. She is the author of four books: The Practitioner's Handbook for Probate Real Estate , The Asset Manager's Guide to Real Estate Owned (REO) , The Real Estate Agent's Ultimate Guide to Real Estate Owned (REO) , and Introduction to Real Estate Sales For Fiduciaries.
Related reading
- Selling a Probate Property in California: A Step-by-Step Guide
- Selling a Trust Property in California: A Guide for Successor Trustees
- How to Sell an Inherited House in California: A Guide for Heirs
- How to Sell a House in a Conservatorship in California
- How to Sell REO (Bank-Owned) Property in California
- Permits, Contractor Licensing and Bids for Pre-Sale Repairs in California: A 2026 Guide
- Property Management for REO and Receivership Properties in California: A 2026 Guide for Lenders, Asset Managers and Receivers
- Repairs Before a Probate or Trust Sale: Sell As-Is or Fix and Sell? A 2026 California Guide
- Selling Bank-Owned Commercial and Multifamily Property in California: A Guide for Lenders and Asset Managers
- Selling Multifamily Property in a California Receivership or REO: A 2026 Guide for Lenders, Receivers and Buyers
- All Geffen guides
- Contact Geffen Real Estate
Disclaimer
This guide is for general information only. It is not legal or tax advice, and it does not create an attorney-client or broker-client relationship. Statutes and local ordinances change; confirm the current text before relying on any section. Last reviewed: November 20, 2026.
Sources
Official sources fetched and read on November 19-20, 2026 (California Legislative Information, leginfo.legislature.ca.gov, via the Legislature's official bulk database snapshot dated November 15, 2026, unless noted):
- California Civil Code, foreclosure property maintenance: § 2929.3; § 2929.4; § 2929.45
- California Business and Professions Code, contractors: § 7026; § 7026.1; § 7028; § 7031; § 7044; § 7048; § 7057; § 7059; § 7071.5; § 7071.6; § 7125; § 7151; § 7159; § 7159.5; § 10176. Chaptered bill: AB 2622 (Stats. 2024, ch. 240)
- California Civil Code, works of improvement: § 8018; § 8046; § 8122; § 8132; § 8136; § 8180; § 8182; § 8190; § 8200; § 8202; § 8204; § 8400; § 8404; § 8410; § 8412; § 8414; § 8416; § 8460
- California Civil Code, other: § 1102.2; § 1954; § 2079. California Probate Code: § 16052
- Contractors State License Board: Check a License; How do I find the right licensed contractor?; How to Prevent a Mechanics Lien
- City of Los Angeles: Los Angeles Municipal Code § 91.106, Permits; Los Angeles Department of Building and Safety; LADBS Information Bulletin P/GI 2026-003, Express Permits (No Plan Check Required)
- Geffen Real Estate: REO and Default Solutions; Property Management; Probate, Trust and Conservatorship