Permits, Contractor Licensing and Bids for Pre-Sale Repairs in California: A 2026 Guide
By Orit Gadish, President and Broker, Geffen Real Estate
Last reviewed: November 20, 2026
This guide is general information for executors, administrators, trustees, conservators, lenders, asset managers and owners who plan to repair a California house before selling it. It is not legal advice. It covers the three practical questions that come up on every pre-sale repair: does the work need a permit, who is allowed to do it, and how to collect and compare bids without leaving a lien on the title. The statutes are quoted from the official text, with a link for each.
Quick answer
Permits are local; the license rules are statewide. Every city and county sets its own permit rules. As one example, the City of Los Angeles says "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" without a permit, and then lists exceptions ( LAMC § 91.106.1.1; § 91.106.2). State law ties the two together in one place: the small-job exception from contractor licensing applies only if "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)). So the first step is to ask the local building department whether the scope needs a permit.
A contractor must be licensed, and the owner pays the price if not. Acting as a contractor without a license is a misdemeanor ( Business and Professions Code § 7028(a)). The civil rule is the one that matters to a seller: "a person who utilizes the services of an unlicensed contractor may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor for performance of any act or contract" ( Business and Professions Code § 7031(b)). The Contractors State License Board lets anyone check a license online, and the board's guidance is to "Get at least three written bids on your project, and make sure you're comparing bids based on identical plans, specifications, and scope of work" ( CSLB).
Bids and contracts decide whether a lien shows up at closing. A contract for repair work on a residence can be a home improvement contract, which must be in writing before work starts and carries a mechanics lien warning ( Business and Professions Code § 7159). Subcontractors and suppliers protect their lien rights by giving a preliminary notice within 20 days of first furnishing work ( Civil Code § 8204(a)), and the owner shortens everyone's deadline by recording a notice of completion ( Civil Code § 8182(a)). Geffen Real Estate has 8 offices throughout California and lists a network of licensed, bonded and fully insured contractors, and a pre-sale renovation option, among its services. If a broker or anyone affiliated with it recommends or coordinates a contractor, ask in writing what the broker is paid in connection with the work.
Key takeaways
- Ask the building department first. Permit thresholds differ by city and county. In Los Angeles, for example, work "valued at $2,500 or less" is exempt unless it affects structure, safety, a Department order or use ( LAMC § 91.106.2).
- A permit is not a blessing of the work. In Los Angeles, "The issuance of a permit is not an approval or an authorization of the work specified therein" ( LAMC § 91.106.4.3.1), and the work is inspected in stages.
- The licensing definition is broad. A contractor is anyone who "submits a bid to" or does the work, and it includes subcontractors and specialty contractors ( Business and Professions Code § 7026).
- Advertising counts. It is a misdemeanor to advertise for construction work "unless that person holds a valid license under this chapter in the classification so advertised" ( Business and Professions Code § 7027.1(a)).
- The $1,000 small-job exception took effect in its current form on January 1, 2025 ( AB 2622), and the section was amended again effective January 1, 2026 ( Business and Professions Code § 7048). It does not apply to a job that needs a building permit.
- Every licensed contractor must put the license number on bids, contracts and ads: "subcontracts and calls for bid" are listed ( Business and Professions Code § 7030.5).
- The license bond is $25,000 ( Business and Professions Code § 7071.6(a)), and the CSLB cautions that bonds "do not assure the financial or professional integrity or competency of a contractor" ( CSLB).
- A subcontractor or supplier loses lien rights if it does not give preliminary notice on time, but "A laborer is not required to give preliminary notice" ( Civil Code § 8200(e)).
- A lien claim dies if not enforced in time: "The claimant shall commence an action to enforce a lien within 90 days after recordation of the claim of lien" ( Civil Code § 8460(a)).
- Examples in this guide that use days or dollar figures are illustrations, not market data.
Plain-English glossary
- Building permit. The local government's authorization to start work that its code covers. It is tied to inspections.
- CSLB. The Contractors State License Board, the state agency that licenses contractors and investigates complaints.
- License classification. The kind of work a license covers, such as general building contractor or a specialty trade.
- Bid. A contractor's written price for a defined scope. In licensing law, the definition of a contractor includes a person who "submits a bid to" do the work ( Business and Professions Code § 7026).
- Home improvement contract. A contract for repair or improvement of residential property, with its own required terms.
- Preliminary notice. The notice a subcontractor or supplier gives to protect lien rights.
- Mechanics lien. A recorded claim against the property by someone who provided work and was not paid.
- Notice of completion. The owner's recorded notice that the work is finished. It starts shorter lien deadlines.
- Lien release bond. A bond that releases the property from a recorded lien so a sale can close while the dispute continues.
Which rule applies? A quick map
| Question | Where the rule is | What it says in short |
|---|---|---|
| Does the job need a permit? | Local building code, such as LAMC § 91.106 | Set by the city or county; Los Angeles lists exempt work |
| Who must be licensed? | B&P § 7026, § 7028 | Anyone acting as a contractor, including subcontractors and those who submit bids |
| Is there a small-job exception? | B&P § 7048 | Under $1,000, no building permit needed, no contractor advertising, no employees (current form effective January 1, 2025) |
| May an owner do the work personally? | B&P § 7044 | The do-it-yourself exemption is not for improvements intended or offered for sale; the direct-contract exemption is limited to four homes offered for sale a year unless a licensed general contractor is hired |
| What can a contractor advertise? | B&P § 7027.1, § 7027.2 | Only licensed classifications; an unlicensed person only under $1,000 and with a disclosure |
| What must a license bond and insurance be? | B&P § 7071.6, § 7125 | $25,000 bond; workers' compensation certificate unless no employees and not a roofing, concrete, HVAC, asbestos or tree-service license; the no-employee exemption ends January 1, 2028 for most licensees |
| What must the contract say? | B&P § 7159, § 7159.5 | Writing before work, license number, change orders, down payment cap, lien warning, three-day right to cancel |
| Who can put a lien on the property? | Civil Code §§ 8400 to 8404 | Contractors, subcontractors, suppliers, laborers, design professionals |
| How do I clear a lien for closing? | Civil Code § 8424, § 8480, § 8490 | Pay and record a release, record a lien release bond, petition for a release order if no timely suit, or record a court order or judgment under § 8490 |
Typical sequence
- Write the scope room by room and trade by trade.
- Ask the local building department which parts need a permit, and who may pull it.
- Pick the license classifications the work requires.
- Ask at least three contractors to bid on the same scope, and collect license numbers.
- Check each license, bond, insurance and subcontractor list before anyone starts.
- Sign a written contract that meets Business and Professions Code § 7159 before work begins.
- Track preliminary notices, pay against the schedule, and collect releases at every payment.
- Schedule permit inspections as work progresses.
- At completion, record the notice of completion and send the required copies.
- Keep the permit, inspection, license and release file for the sale.
Step 1: Write the scope and ask about permits
A bid is only as good as the scope behind it. Write down each room or area, the trades involved, and what is excluded, then ask the building department of the city or county where the property sits whether any item needs a permit. The state licensing law links the two: the small-job exception applies only if "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)).
The City of Los Angeles is a useful example of how a permit rule reads. Its code says "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" and continues "unless said person has obtained a permit therefor from the department" ( LAMC § 91.106.1.1). Permits are not required for listed work, including "Work regulated by this Code that is valued at $2,500 or less, unless it impacts the structural stability of a building, affects public safety, is performed to comply with a Department order, or involves a change in the use or occupancy" ( LAMC § 91.106.2). The code also says "Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of the City of Los Angeles" ( LAMC § 91.106.2). Other cities and counties set their own lists and dollar thresholds. The Los Angeles Department of Building and Safety publishes a list of work that can get an express permit without plan check: "Following are the lists of different types of construction for which an express permit can be issued" ( LADBS Information Bulletin P/GI 2026-003, revised June 10, 2026). The list includes "Kitchen/bathroom remodel for residential buildings (no structural changes)" and "Replacing water heaters" ( LADBS Information Bulletin P/GI 2026-003). Whether a particular job qualifies is for LADBS to say.
An application identifies the work. In Los Angeles, every application must "Identify and describe the work to be covered by the permit for which application is made" and "Describe the land on which the proposed work is to be done by legal description, street address or similar description that will readily identify and definitely locate the proposed building or work" ( LAMC § 91.106.3.1). The department "shall issue a permit upon receipt of the total fees" once the information conforms to the code ( LAMC § 91.106.4.1).
Step 2: Understand who needs a license
The definition. A contractor is "any person who undertakes to or offers to undertake to, or purports to have the capacity to undertake to, or submits a bid to, or does himself or herself or by or through others, construct, alter, repair, add to, subtract from, improve, move, wreck or demolish any building" ( Business and Professions Code § 7026), and the term "includes subcontractor and specialty contractor" ( Business and Professions Code § 7026).
Project managers and coordinators count too. A "consultant" is a contractor, and for home improvement work a consultant includes a person, other than the owner, who "Provides or oversees a bid for a construction project" or who "Arranges for and sets up work schedules for contractors and subcontractors and maintains oversight of a construction project" ( Business and Professions Code § 7026.1(a)(2)(B)). Paying an unlicensed project manager or renovation coordinator carries the same payment risk as paying an unlicensed contractor ( Business and Professions Code § 7031(b)).
The crime and the civil consequence."it is a misdemeanor for a person to engage in the business of, or act in the capacity of, a contractor within this state" when "The person is not licensed in accordance with this chapter" ( Business and Professions Code § 7028(a)). A first conviction is "punishable by a fine not exceeding five thousand dollars ($5,000) or by imprisonment in a county jail not exceeding six months, or by both that fine and imprisonment" ( Business and Professions Code § 7028(b)). The person who hired the unlicensed worker is treated as a victim: "a person who utilized the services of the unlicensed person is a victim of crime" ( Business and Professions Code § 7028(h)). Civilly, an unlicensed contractor generally cannot sue for payment, because a contractor must allege "that they were a duly licensed contractor at all times during the performance of that act or contract" ( Business and Professions Code § 7031(a)), and the owner may recover "all compensation paid to the unlicensed contractor" ( Business and Professions Code § 7031(b)). When licensure is disputed, "the burden of proof to establish licensure or proper licensure shall be on the licensee" ( Business and Professions Code § 7031(d)).
Advertising."It is a misdemeanor for any person to advertise for construction or work of improvement covered by this chapter unless that person holds a valid license under this chapter in the classification so advertised" ( Business and Professions Code § 7027.1(a)). An unlicensed person may advertise only "if the aggregate contract price for labor, material, and all other items on a project or undertaking is less than one thousand dollars ($1,000) and the person states in the advertisement that the person is not licensed under this chapter" ( Business and Professions Code § 7027.2).
The small-job exception. The licensing chapter "does not apply to a work or operation on one undertaking or project by one or more contracts if the aggregate contract price for labor, materials, and all other items is less than one thousand dollars ($1,000)," and only where the work "does not require a building permit" ( Business and Professions Code § 7048(a)). The $1,000 figure, the building-permit condition and the employee condition took effect January 1, 2025 ( AB 2622, Stats. 2024, ch. 240); the section was amended again effective January 1, 2026 (Stats. 2025, ch. 67, per the section's history line). Splitting a larger job into small contracts does not qualify: the exception does not apply where "a division of the operation is made in contracts of amounts less than one thousand dollars ($1,000) for the purpose of evasion of this chapter or otherwise" ( Business and Professions Code § 7048(b)). It also does not apply to a person who "Advertises or puts out a sign or card or other device that might indicate to the public that the person is a contractor" or who "Employs another person to perform, or assist in performing, the work or operation" ( Business and Professions Code § 7048(c)).
The owner-builder exemption. The exemption for an owner who does the work personally or with the owner's own employees does not apply when the improvements are intended for sale. It requires that "None of the improvements are intended or offered for sale" ( Business and Professions Code § 7044(a)(1)(A)), and that "The property owner personally performs all of the work or any work not performed by the owner is performed by the owner's employees with wages as their sole compensation" ( Business and Professions Code § 7044(a)(1)(B)). A separate exemption covers an owner that contracts directly with licensed trade contractors: "The owner directly contracts with licensees who are duly licensed to contract for the work of the respective trades involved in completing the project" ( Business and Professions Code § 7044(a)(2)(A)). For single-family homes that exemption is limited: "no more than four of these structures are intended or offered for sale in a calendar year," and the limit "shall not apply if the owner contracts with a general contractor for the construction" ( Business and Professions Code § 7044(a)(2)(B)). Proof that five or more structures were sold or offered for sale within a year after completion "constitutes a conclusive presumption that the structures were undertaken for purposes of sale" ( Business and Professions Code § 7044(b)(2)). For a lender, the practical path is a licensed general contractor.
Classification. A general building contractor is one whose work involves "the use of at least two unrelated building trades or crafts" ( Business and Professions Code § 7057(a)), and a general building contractor "shall not take a prime contract for any project involving trades other than framing or carpentry" unless certain conditions are met, including that the contractor "holds the appropriate license classification or subcontracts with an appropriately licensed contractor to perform the work" ( Business and Professions Code § 7057(b)). The board may "limit the field and scope of the operations of a licensed contractor to those in which they are classified and qualified to engage" ( Business and Professions Code § 7059(a)). So the license check should include the classification, not just the status.
Hazardous materials."It is a misdemeanor for any contractor, whether licensed or unlicensed, to perform or engage in asbestos-related work" without the required certification ( Business and Professions Code § 7028.1). If a scope may disturb materials in an older house, put that question in the bid request.
Step 3: Check the license, the bond and the insurance
The lookup. The CSLB's license check lets you "Look up a contractor license or Home Improvement Salesperson (HIS) registration to verify information, including complaint disclosure" ( CSLB, Check a License). The board's consumer page adds that "Contractors are required to have their license number on their business card and on all bids and contracts," that "Seeing a license number doesn't necessarily mean the license is valid," and that you should check the status ( CSLB). The statute requires the number: a licensed person "shall include his license number" in contracts, "subcontracts and calls for bid," and advertising ( Business and Professions Code § 7030.5).
The salesperson. A home improvement salesperson must register, and "prior to engaging in any activity" must "identify to the owner or tenant the business name and license number of the contractor they are representing" ( Business and Professions Code § 7152(c)). The CSLB advises: "When the contractor comes to your house to give you a bid, ask to see their pocket license, along with a picture I.D." ( CSLB).
The bond. The board "shall require" a license bond "in the sum of twenty-five thousand dollars ($25,000)" ( Business and Professions Code § 7071.6(a)). The CSLB explains: "This bond covers any project the contractor agrees to perform. Be aware: this bond is often not enough to cover multiple complaints made against it or your project if it's worth more than the value of the bond" ( CSLB). The bond protects a narrow group first. For claims other than those of the beneficiaries listed in § 7071.5(a), including "A homeowner contracting for home improvement upon the homeowner's personal family residence damaged as a result of a violation of this chapter by the licensee" ( Business and Professions Code § 7071.5(a)), "the aggregate liability of a surety on claims brought against a bond required by this section shall not exceed the sum of seven thousand five hundred dollars ($7,500)" ( Business and Professions Code § 7071.6(b)). For a larger job, a contract bond is a different product: "Contract bonds guarantee both the completion of the job and payment for all labor and materials" ( CSLB).
Workers' compensation. A licensee must "have on file at all times a current and valid Certificate of Workers' Compensation Insurance or Certification of Self-Insurance in the applicant's or licensee's business name" ( Business and Professions Code § 7125(a)). The exception is narrow: the section does not apply to a licensee who meets "both of the following conditions" ( Business and Professions Code § 7125(b)). The first is that the licensee "Has no employees" and files a statement saying so ( § 7125(b)(1)). The second is that the licensee "Does not hold a C-8 license" (concrete), "a C-20 license" (HVAC), "a C-22 license" (asbestos abatement), "a C-39 license" (roofing), "or a D-49 license" (tree service) ( § 7125(b)(2)). So a contractor with no employees still needs the certificate if it holds one of those licenses. This version of the section "shall remain in effect only until January 1, 2028" ( § 7125(i)). Under the version operative January 1, 2028, the exemption for a licensee with no employees ends for everyone except a joint venture: "This section does not apply to an applicant or licensee organized as a joint venture pursuant to Section 7029 that has no employees" ( § 7125(b), operative January 1, 2028). The CSLB warns that "If a worker is injured working on your property and the contractor doesn't have insurance, you could be financially liable to pay for injuries and rehabilitation" ( CSLB).
A simple checklist for the file. Keep the license printout, the insurance certificate, the subcontractor list and the picture ID check together with the bid.
Step 4: Collect and compare bids
The CSLB's guidance for bids is direct: "Get at least three written bids on your project, and make sure you're comparing bids based on identical plans, specifications, and scope of work" and "Do not automatically accept the lowest bid" ( CSLB). It adds a warning about bids that are far too low: "you should beware of any bid that is substantially lower than the others" ( CSLB).
A practical bid comparison sheet has the same columns for every bidder:
| Item to compare | What to look for |
|---|---|
| License number and classification | Matches the work; active on the CSLB lookup |
| Scope | Same rooms, trades and exclusions as your written scope |
| Price | Labor and materials shown separately where the bid allows |
| Permits | Who pulls each permit and who pays the fee |
| Schedule | Start date, completion date, and what counts as substantial start |
| Payment terms | Down payment within the statutory cap; progress payments tied to described work |
| Subcontractors | Named, licensed, and listed in the contract |
| Insurance | Workers' compensation certificate or no-employee statement; general liability disclosure |
| Lien handling | Releases with each payment; who gives preliminary notices |
This table is a practical tool, not a statutory form. The items are drawn from the contract rules in the next step and from the CSLB's consumer guidance.
Step 5: The written contract
A contract between a contractor and an owner for repair of residential property fits the home improvement definition on its face. "Home improvement" means "the repairing, remodeling, altering, converting, or modernizing of, or adding to, residential property" ( Business and Professions Code § 7151(a)). A home improvement contract is "an agreement, whether oral or written, or contained in one or more documents, between a contractor and an owner" where the price "exceeds five hundred dollars ($500)" ( Business and Professions Code § 7159(b)).
| Requirement | What the statute says |
|---|---|
| Signed before work | "Before any work is started, the contractor shall give the buyer a copy of the contract that is signed and dated by both the contractor and the buyer" ( § 7159(c)(3)(A)) |
| Contractor identity | "The name, business address, and license number of the contractor" ( § 7159(d)(1)) |
| Price | The heading "Contract Price," followed by the amount in dollars and cents ( § 7159(d)(5)) |
| Change orders | "shall become part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by a change order" ( § 7159(c)(5)) |
| Bond notice | "a notice stating that the owner or tenant has the right to require the contractor to have a performance and payment bond" ( § 7159(c)(6)) |
| Subcontractors | "The contract shall contain a statement regarding whether or not a subcontractor will be used on the project" ( § 7159(c)(7)(A)) |
| Down payment | "the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less" ( § 7159.5(a)(3)) |
| Progress payments | "IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED" ( § 7159(d)(9)(C)) |
| Lien releases | The contractor "shall furnish to the person contracting for the home improvement or swimming pool work a full and unconditional release from any potential lien claimant claim or mechanics lien" for the portion paid ( § 7159(c)(4)). Under the companion section, releases are furnished "if requested" ( § 7159.5(a)(6)), so ask for them with each payment |
| Right to cancel | Unless the contract was "Negotiated at the contractor's place of business" or another listed exception applies, the buyer must get a notice entitled "Three-Day Right to Cancel" ("Five-Day Right to Cancel" for a senior citizen) ( § 7159(e)(6)) |
| Bonded contractors | A contractor "furnishing a performance and payment bond, lien and completion bond, or a bond equivalent or joint control approved by the registrar covering full performance and payment is exempt from paragraphs (3), (4), and (5)" of the payment rules ( § 7159.5(a)(8)) |
| Lien warning | "Anyone who helps improve your property, but who is not paid, may record what is called a mechanics lien on your property" ( § 7159(e)(4)) |
The statute has more required headings, notices and dates than this table shows. Check any contract form against the current text of § 7159.
Step 6: Preliminary notices from subcontractors and suppliers
Even when the owner pays the main contractor in full, unpaid subcontractors and suppliers can reach the property. The lien statute's first protection for owners is the preliminary notice. Before recording a lien claim, "a claimant shall give preliminary notice to the following persons" ( Civil Code § 8200(a)): the owner, the direct contractor, and any construction lender. "Compliance with this section is a necessary prerequisite to the validity of a lien claim or stop payment notice under this title" ( Civil Code § 8200(c)).
The exceptions are narrow: "A laborer is not required to give preliminary notice," and a claimant with a direct contract with the owner gives notice "only to the construction lender or reputed construction lender, if any" ( Civil Code § 8200(e)).
The timing rule is "not later than 20 days after the claimant has first furnished work on the work of improvement" ( Civil Code § 8204(a)). A late notice is not worthless, but it is limited: the claimant is entitled to a lien "only for work performed within 20 days prior to the service of the preliminary notice, and at any time thereafter" ( Civil Code § 8204(a)). A claimant "need give only one preliminary notice to each person to which notice must be given under this chapter with respect to all work provided by the claimant for a work of improvement," but must give a separate notice for each subcontract if it works for more than one subcontractor ( Civil Code § 8206).
The notice carries a plain warning to the owner: "EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property" ( Civil Code § 8202(a)(3)).
Two rules help the owner track who is on the job. "A direct contractor shall make available to any person seeking to give preliminary notice the following information": the name and address of the owner, and the name and address of the construction lender, if any ( Civil Code § 8208). And a permit application itself has a space for a lender: a public entity that issues building permits "shall, in its application form for a building permit, provide space and a designation for the applicant to enter the name, branch designation, if any, and address of the construction lender" ( Civil Code § 8172(a)).
The CSLB's advice for owners is to "Save Preliminary Notices and note the date received so you can keep track of who is owed money and when they are paid" ( CSLB, How to Prevent a Mechanics Lien).
Step 7: Mechanics liens: who, how and how long
Who has lien rights."A person that provides work authorized for a work of improvement" has a lien right, including a "Direct contractor," "Subcontractor," "Material supplier," "Equipment lessor," "Laborer," and "Design professional" ( Civil Code § 8400). Work is authorized when "It is provided at the request of or agreed to by the owner" or "provided or authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of all or part of the work of improvement or site improvement" ( Civil Code § 8404). The same applies if the listing broker or any coordinator is "having charge" of the work: its orders can make the work authorized for lien purposes ( Civil Code § 8404(b)). Keep change orders in the owner's name and in writing.
How much. The lien is "a direct lien for the lesser of the following amounts": "The reasonable value of the work provided by the claimant" or "The price agreed to by the claimant and the person that contracted for the work" ( Civil Code § 8430(a)).
What the claimant must do. A claimant "may enforce a lien only if the claimant has given preliminary notice to the extent required" and "made proof of notice" ( Civil Code § 8410). A claim of lien "shall be a written statement, signed and verified by the claimant" ( Civil Code § 8416(a)), and a copy including the statutory Notice of Mechanics Lien "shall be served on the owner or reputed owner" ( Civil Code § 8416(c)). If service is not made as the statute prescribes, the claim is "unenforceable as a matter of law" ( Civil Code § 8416(e)). The Notice of Mechanics Lien tells the owner: "Upon the recording of the enclosed MECHANICS LIEN with the county recorder's office of the county where the property is located, your property is subject to the filing of a legal action seeking a court-ordered foreclosure sale of the real property on which the lien has been recorded" ( Civil Code § 8416(a)(8)).
The deadlines. A direct contractor must record a claim before the earlier of "Ninety days after completion of the work of improvement" or "Sixty days after the owner records a notice of completion or cessation" ( Civil Code § 8412). Other claimants must record before the earlier of "Ninety days after completion of the work of improvement" or "Thirty days after the owner records a notice of completion or cessation" ( Civil Code § 8414). Then the claimant has "90 days after recordation of the claim of lien" to sue, or "the claim of lien expires and is unenforceable" ( Civil Code § 8460(a)).
| Illustration (days counted from completion) | Direct contractor deadline to record | Subcontractor or supplier deadline to record |
|---|---|---|
| No notice of completion recorded | Day 90 | Day 90 |
| Notice of completion recorded on day 10 | Day 70 | Day 40 |
The table illustrates how §§ 8412 and 8414 work. It is not a calendar for any particular job.
Clearing a lien for closing. There are four paths, and the owner's attorney handles the filings.
- Pay or settle, and record a release. If the claim is valid or is settled, the claimant records a release, and the title company will want to see it recorded.
- Record a lien release bond. An owner "that disputes the correctness or validity of the claim may obtain release of the real property from the claim of lien by recording a lien release bond" ( Civil Code § 8424(a)), in "an amount equal to 125 percent of the amount of the claim of lien" and executed by an admitted surety insurer ( Civil Code § 8424(b)). On recording, "the real property is released from the claim of lien and from any action to enforce the lien" ( Civil Code § 8424(c)). The bond does not end the claim: "The claimant shall commence an action on the bond within six months after notice is given" ( Civil Code § 8424(d)).
- Petition for a release order. When the claimant never sued in time, the owner "may petition the court for an order to release the property from the claim of lien if the claimant has not commenced an action to enforce the lien within the time provided in Section 8460" ( Civil Code § 8480(a)), after giving at least 10 days' notice demanding that the claimant record a release ( Civil Code § 8482).
- Record a court order or judgment."A court order or judgment under this section is equivalent to cancellation of the claim of lien and its removal from the record" ( Civil Code § 8490(b)). That section "does not apply to a court order dismissing an action to enforce a lien that is expressly stated to be without prejudice" ( Civil Code § 8490(d)).
Practice note: a claim that has expired under § 8460 is unenforceable, but ask your title company whether it will insure over the recorded claim or wants a recorded release before closing.
Step 8: Pay in a way that protects the title
Waivers cannot be taken from someone else."An owner, direct contractor, or subcontractor may not, by contract or otherwise, waive, affect, or impair any other claimant's rights under this part" ( Civil Code § 8122). A claimant's own waiver works only in the statutory form. A progress-payment waiver where the claimant is not actually paid is "null, void, and unenforceable unless it is in substantially the following form" ( Civil Code § 8132). The final-payment form is in § 8136.
Practical steps from the CSLB. The board's consumer guidance says to "Get a list of all subcontractors, laborers, and material suppliers to be used by your direct contractor" and "Before making a payment, get a signed conditional release from the possible lien claimants" ( CSLB, How to Prevent a Mechanics Lien). It says "By law, you may withhold the next payment until you get the unconditional releases for the previous payment," and calls joint checks "The simplest way to prevent liens and ensure that subcontractors and suppliers are paid" ( CSLB).
Step 9: Inspections and completion
In Los Angeles, "The issuance of a permit is not an approval or an authorization of the work specified therein. A permit is merely an application for inspection" ( LAMC § 91.106.4.3.1). The Department of Building and Safety describes its role: "We review plans, issue permits, and inspect the work" ( LADBS). It explains that "Once each stage is completed, the work will need to be inspected and approved before covering up the work and moving onto the next stage" ( LADBS), and that it responds to complaints about "construction done or in-progress without permits" ( LADBS). Keep the final inspection record for the sale file.
Legal completion also matters for the lien clock. It occurs on "Actual completion of the work of improvement," "Occupation or use by the owner accompanied by cessation of labor," "Cessation of labor for a continuous period of 60 days," or "Recordation of a notice of cessation after cessation of labor for a continuous period of 30 days" ( Civil Code § 8180(a)). The owner may record a notice of completion "on or within 15 days after the date of completion of a work of improvement" ( Civil Code § 8182(a)), signed and verified by the owner ( Civil Code § 8182(b)). An owner that records it "shall, within 10 days of the date the notice of completion or cessation is filed for record, give a copy of the notice" to the direct contractor and each claimant that gave preliminary notice ( Civil Code § 8190(a)); if not, "the notice is ineffective to shorten the time within which that person may record a claim of lien under Sections 8412 and 8414" ( Civil Code § 8190(c)).
Who is the owner? A note for fiduciaries and lenders
The same steps apply whether the owner is an individual, an estate, a trust, a conservatorship or a lender. A fiduciary also has to confirm authority to spend, and the source of that authority differs for each role. Our guides on selling probate property, selling trust property and selling conservatorship property cover authority and notice, and our guide on selling REO property covers the lender's maintenance duties. For a trustee, the code also says "not to use or deal with trust property for the trustee's own profit" and not "to take part in any transaction in which the trustee has an interest adverse to the beneficiary" ( Probate Code § 16004(a)). If a broker or anyone affiliated with it recommends or coordinates the contractor, ask in writing what the broker is paid in connection with the work, and get competing bids. A licensee must not fail "to reveal to the buyer or seller contracting with the licensee the full amount of the licensee's compensation, commission, or profit" before the agreement is signed ( Business and Professions Code § 10176(g)). A trustee "shall exercise prudence in" "Selecting an agent" ( Probate Code § 16052(a)).
For lenders: Read together, § 8190(d)(3) and § 1102.2(c) indicate that a lender that took title at its own trustee's sale or by a deed in lieu of foreclosure is not subject to the 10-day copy duty. Section 8190(d) says the section does not apply to "A person that obtains an interest in the property pursuant to a transfer described in subdivision (b), (c), or (d) of Section 1102.2" ( Civil Code § 8190(d)(3)), and § 1102.2(c) covers "sales to a beneficiary of a deed of trust by a trustor or successor in interest who is in default" and sales "by a mortgagee or a beneficiary under a deed of trust who has acquired the real property at a sale conducted pursuant to a power of sale" ( Civil Code § 1102.2(c)). For an owner that is subject to the duty, not giving the copies means the notice is ineffective to shorten the claimant's time, which "is the sole liability of the owner for failure to give notice" ( Civil Code § 8190(c)). Some lenders send the copies anyway, because it costs little and removes any argument about the deadline. Ask counsel how your institution handles it.
The estate's, trust's or lender's attorney handles questions of authority, contract terms and lien disputes.
How Geffen Real Estate can help
The services on our site that matter to pre-sale repairs include:
- Pre-sale renovation for REO. Our REO and Default Solutions page lists a renovation option before sale. See that page for the current description.
- Contractor network. On our property management page, we list a network of licensed, bonded and fully insured contractors who have been vetted for good pricing and work that is up to code.
- Renovate now, pay at closing. On our probate, trust and conservatorship page, we list repairs done first with the cost paid at the close of escrow. Some clients prefer to sell as-is, and we support either strategy.
- Value opinions. We provide BPO and BOV reports, which can compare the as-is and repaired scenarios.
- Marketing, offer management and escrow management once the property is ready to list.
Before using any renovation program, ask who signs the contract with the contractor and who holds the contractor license. If Geffen or any broker is paid anything connected with the repairs, the full amount must be disclosed in writing before you sign ( Business and Professions Code § 10176(g)).
These services are optional. They do not guarantee a higher price, a faster sale or a particular result, and they are not legal advice.
Frequently asked questions
Do I need a permit to repair a house before selling it in California?
It depends on the work and on the city or county. Permit rules are local. In the City of Los Angeles, "No person shall erect, construct, alter, repair, demolish, remove or move any building or structure" without a permit ( LAMC § 91.106.1.1), with exceptions such as work "valued at $2,500 or less" that does not affect structure, safety or use ( LAMC § 91.106.2). Ask the building department where the property is.
How do I find out whether a repair needs a permit in Los Angeles?
Start with the Los Angeles Department of Building and Safety. It describes its role as "We review plans, issue permits, and inspect the work" ( LADBS), and publishes an express permit list. Its bulletin says "Following are the lists of different types of construction for which an express permit can be issued" ( LADBS Information Bulletin P/GI 2026-003, revised June 10, 2026). The list includes "Kitchen/bathroom remodel for residential buildings (no structural changes)" and "Replacing water heaters" ( LADBS Information Bulletin P/GI 2026-003). Whether a particular job qualifies is for LADBS to say. The municipal code lists the work that needs no permit ( LAMC § 91.106.2).
Who can pull a building permit in Los Angeles?
LADBS says "You may obtain the permit as an Agent, an Owner, or a Contractor" ( LADBS). Other jurisdictions have their own rules about who may apply.
Does a permit mean the work is approved?
No. In Los Angeles, "The issuance of a permit is not an approval or an authorization of the work specified therein" ( LAMC § 91.106.4.3.1). The work is inspected in stages before it is covered.
Does a contractor need a license for small repairs in California?
Below a small threshold, no. The licensing chapter does not apply where the total price is "less than one thousand dollars ($1,000)" and "the work or operation does not require a building permit" ( Business and Professions Code § 7048(a)). Above that, or if the job needs a permit, a license is required. The $1,000 figure, the building-permit condition and the employee condition took effect January 1, 2025 ( AB 2622, Stats. 2024, ch. 240); the section was amended again effective January 1, 2026 (Stats. 2025, ch. 67, per the section's history line).
Can a handyman who is not licensed do repairs on a house I am selling?
Only within the small-job exception. The exception does not apply to someone who advertises as a contractor or who employs another person to do the work ( Business and Professions Code § 7048(c)), and it does not apply to a job split into pieces "for the purpose of evasion of this chapter or otherwise" ( Business and Professions Code § 7048(b)).
Is it illegal to hire an unlicensed contractor, and what happens if I do?
You may recover what you paid: "a person who utilizes the services of an unlicensed contractor may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor for performance of any act or contract" ( Business and Professions Code § 7031(b)). The contractor generally cannot sue you for payment ( Business and Professions Code § 7031(a)). Hiring one is not itself the crime. The misdemeanor is acting as a contractor without a license: "it is a misdemeanor for a person to engage in the business of, or act in the capacity of, a contractor within this state" ( Business and Professions Code § 7028(a)), and the code treats the person who hired the unlicensed worker as a victim ( Business and Professions Code § 7028(h)). The owner still carries practical risks: no license bond to claim against, no workers' compensation certificate on file, and a contract that may be hard to enforce. See the workers' compensation point in Step 3.
How do I check a contractor's license?
Use the Contractors State License Board's license check. It lets you "Look up a contractor license or Home Improvement Salesperson (HIS) registration to verify information, including complaint disclosure" ( CSLB). Check the classification and the status, and compare the name on the pocket license with a picture ID.
What should a contractor's bid include?
At minimum, the license number, a scope that matches yours, a price, a schedule, payment terms and the subcontractors. The CSLB says "Contractors are required to have their license number on their business card and on all bids and contracts" ( CSLB), and the statute lists "subcontracts and calls for bid" among the places a licensee must show the number ( Business and Professions Code § 7030.5).
How many bids should I get for pre-sale repairs?
The CSLB's advice is "Get at least three written bids on your project," compared on "identical plans, specifications, and scope of work" ( CSLB). It also advises: "Do not automatically accept the lowest bid" ( CSLB).
How much can a contractor ask for as a down payment?
"the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less" ( Business and Professions Code § 7159.5(a)(3)). A contractor that furnishes an approved performance and payment bond is exempt from that cap and the related payment rules ( Business and Professions Code § 7159.5(a)(8)).
Does the repair contract have to be in writing?
If it is a home improvement contract, yes. It must "be in writing and signed by the parties to the contract prior to the commencement of work covered by the contract" ( Business and Professions Code § 7159(d)). Change orders must also be in writing and signed before the extra work starts ( Business and Professions Code § 7159(c)(5)).
What is the contractor license bond, and is it enough?
Licensed contractors must have a bond "in the sum of twenty-five thousand dollars ($25,000)" ( Business and Professions Code § 7071.6(a)). The CSLB cautions that it "is often not enough to cover multiple complaints made against it or your project if it's worth more than the value of the bond" ( CSLB). For claims by others, "the aggregate liability of a surety on claims brought against a bond required by this section shall not exceed the sum of seven thousand five hundred dollars ($7,500)" ( Business and Professions Code § 7071.6(b)).
Does a contractor have to carry workers' compensation insurance?
Yes if it has employees, and roofing, concrete, HVAC, asbestos abatement and tree-service contractors must carry it even without employees ( Business and Professions Code § 7125(b)). The exemption is for a licensee that "Has no employees" and files a statement ( Business and Professions Code § 7125(b)(1)). From January 1, 2028, the no-employee exemption ends for almost all licensees ( Business and Professions Code § 7125(b), operative January 1, 2028). The CSLB explains the owner's risk if a worker is hurt and there is no coverage ( CSLB).
What is a preliminary notice?
It is the notice a subcontractor or supplier gives the owner, the direct contractor and any construction lender before it can record a lien ( Civil Code § 8200(a)). It must come "not later than 20 days after the claimant has first furnished work on the work of improvement" ( Civil Code § 8204(a)).
Can a subcontractor put a lien on my house if I paid the general contractor in full?
It can try, if it gave the required notice. The preliminary notice itself warns: "EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property" ( Civil Code § 8202(a)(3)).
How long does a contractor have to record a mechanics lien, and how long does it last?
A direct contractor has until the earlier of 90 days after completion or 60 days after a recorded notice of completion or cessation ( Civil Code § 8412). Others have until the earlier of 90 days after completion or 30 days after the recorded notice ( Civil Code § 8414). After recording, the claimant "shall commence an action to enforce a lien within 90 days after recordation of the claim of lien," or the claim "expires and is unenforceable" ( Civil Code § 8460(a)). An agreed extension of credit can change the period, as the same section explains.
What is a notice of completion and when do I record it?
It is the owner's signed and verified notice, recorded "on or within 15 days after the date of completion of a work of improvement" ( Civil Code § 8182(a)). It shortens the lien deadlines for claimants, and the owner must send copies as described in Civil Code § 8190.
Can I sell the house if a mechanics lien is recorded?
The lien stays on title until it is released, expires or is cleared. The code lets an owner record a lien release bond for "125 percent of the amount of the claim of lien," after which "the real property is released from the claim of lien and from any action to enforce the lien" ( Civil Code § 8424). If the claimant did not sue in time, the owner may petition for a release order ( Civil Code § 8480(a)), and a recorded court order or judgment under § 8490 is "equivalent to cancellation of the claim of lien and its removal from the record" ( Civil Code § 8490(b)). Paying and recording a release is the fourth path. Step 7 lists all four.
What lien waivers should I get when I pay a contractor?
Get the statutory forms. A conditional waiver and release on a progress payment is enforceable only if it is "in substantially the following form" ( Civil Code § 8132), and the CSLB's guidance is to "get a signed conditional release from the possible lien claimants" before paying ( CSLB).
Does Geffen have a contractor network for pre-sale repairs?
Our property management page lists a network of licensed, bonded and fully insured contractors, and our REO and Default Solutions page lists a renovation option before sale. For probate, trust and conservatorship sales, our probate page lists renovate now, pay at closing. These are optional services with no promised result. Whoever you hire, check the license, get competing bids, and ask in writing what any broker is paid in connection with the work ( Business and Professions Code § 10176(g)).
Can my real estate agent manage the repairs?
Be careful. A person other than the owner who "Provides or oversees a bid for a construction project" or "Arranges for and sets up work schedules for contractors and subcontractors and maintains oversight of a construction project" is treated as a contractor for home improvement work ( Business and Professions Code § 7026.1(a)(2)(B)). Ask who signs the contract with the contractor and who holds the license. If the agent is paid anything connected with the work, the licensee must reveal "the full amount of the licensee's compensation, commission, or profit" before the agreement is signed ( Business and Professions Code § 10176(g)). Get competing bids either way.
Do I have to disclose unpermitted work when I sell?
Ask your attorney how the disclosure rules apply to your type of sale, since some transfers by fiduciaries and lenders are exempt from the seller disclosure statement ( Civil Code § 1102.2). The listing broker's duty is separate: for one to four units, the broker must "conduct a reasonably competent and diligent visual inspection of the property offered for sale and to disclose to that prospective buyer all facts materially affecting the value or desirability of the property that an investigation would reveal" ( Civil Code § 2079(a)).
What is a three-day right to cancel on a repair contract?
For a home improvement contract, the buyer must get a notice entitled "Three-Day Right to Cancel" ("Five-Day Right to Cancel" for a senior citizen) unless the contract was "Negotiated at the contractor's place of business" or another listed exception applies. It says "You, the buyer, have the right to cancel this contract within three business days" ( Business and Professions Code § 7159(e)(6)). Plan the start date around it.
Talk with Geffen Real Estate
If you are an executor, trustee, conservator, lender, asset manager or owner with a California property to prepare and sell, we are glad to talk it through. Call 323-934-1430. Our team answers this line 24 hours a day, 7 days a week. You can also use the contact page. Geffen Real Estate has 8 offices throughout California, with headquarters at 9171 Wilshire Blvd #500, Beverly Hills, CA 90210.
The offices are:
- Beverly Hills (headquarters): 9171 Wilshire Blvd #500, Beverly Hills, CA 90210
- Sacramento: 2740 Fulton Ave, Sacramento, CA 95821
- San Diego: 10089 Willow Creek Rd #200, San Diego, CA 92131
- Irvine: 2102 Business Center Dr #130, Irvine, CA 92612
- San Jose: 2570 N First St, San Jose, CA 95131
- Santa Barbara: 351 Paseo Nuevo, Santa Barbara, CA 93101
- Riverside: 3610 Central Ave #400, Riverside, CA 92506
- Palm Springs: 750 N Palm Canyon Dr #200, Palm Springs, CA 92262
All offices may be reached at 323-934-1430.
About the author
Orit Gadish is the President and broker of Geffen Real Estate (DRE 01505675). The firm has 8 offices throughout California, with headquarters in Beverly Hills, and handles probate, trust, conservatorship and other court-supervised real estate sales as well as REO and default dispositions. She is the author of four books: The Practitioner's Handbook for Probate Real Estate , The Asset Manager's Guide to Real Estate Owned (REO) , The Real Estate Agent's Ultimate Guide to Real Estate Owned (REO) , and Introduction to Real Estate Sales For Fiduciaries.
Related reading
- Selling a Probate Property in California: A Step-by-Step Guide
- Selling a Trust Property in California: A Guide for Successor Trustees
- How to Sell an Inherited House in California: A Guide for Heirs
- How to Sell a House in a Conservatorship in California
- How to Sell REO (Bank-Owned) Property in California
- Managing Pre-Sale Renovations for Lenders and Asset Managers in California: A 2026 Guide
- Repairs Before a Probate or Trust Sale: Sell As-Is or Fix and Sell? A 2026 California Guide
- Selling Commercial Property in a California Probate or Trust: Retail, Office and Industrial
- Selling a Multifamily or Apartment Building in a California Probate or Trust: A 2026 Guide
- Property Management for REO and Receivership Properties in California: A 2026 Guide for Lenders, Asset Managers and Receivers
- All Geffen guides
- Contact Geffen Real Estate
Disclaimer
This guide is for general information only. It is not legal or tax advice, and it does not create an attorney-client or broker-client relationship. Statutes and local ordinances change; confirm the current text before relying on any section. Last reviewed: November 19, 2026.
Sources
Official sources fetched and read on November 19-20, 2026 (California Legislative Information, leginfo.legislature.ca.gov, via the Legislature's official bulk database snapshot dated November 15, 2026, unless noted):
- California Business and Professions Code, contractors: § 7026; § 7026.1; § 7027.1; § 7027.2; § 7028; § 7028.1; § 7030.5; § 7031; § 7044; § 7048; § 7057; § 7059; § 7071.5; § 7071.6; § 7125; § 7151; § 7152; § 7159; § 7159.5; § 10176. Chaptered bill: AB 2622 (Stats. 2024, ch. 240)
- California Civil Code, works of improvement: § 8122; § 8132; § 8136; § 8172; § 8180; § 8182; § 8190; § 8200; § 8202; § 8204; § 8206; § 8208; § 8400; § 8404; § 8410; § 8412; § 8414; § 8416; § 8424; § 8430; § 8460; § 8480; § 8482; § 8490; § 1102.2; § 2079. California Probate Code: § 16004; § 16052
- Contractors State License Board: Check a License; How do I find the right licensed contractor?; How to Prevent a Mechanics Lien
- City of Los Angeles: Los Angeles Municipal Code § 91.106, Permits; Los Angeles Department of Building and Safety; LADBS Information Bulletin P/GI 2026-003, Express Permits (No Plan Check Required)
- Geffen Real Estate: REO and Default Solutions; Property Management; Probate, Trust and Conservatorship